SEPTEMBER 2019
Sunday, September 22 – Saturday, September 28, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, September 28th.
Sunday, September 22, 2019
-
No scheduled construction activity.
Monday, September 23 - Saturday, September 28, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of curb and sidewalk at 14th and U Street NW (Monday - Wednesday).
-
Installation of bumpout and sidewalk between T Street and U Street NW (east side; Wednesday to Friday).
-
Installation of bus island at 14th and Rhode Island Avenue NW (Monday
-
Begin electric line on 14th and R Street NW.
-
Pulling of conductor and push buttons at N Street, P Street, Q Street, V Street and W Street NW.
-
Installation of two 20-ft poles and four 28-ft poles for traffic work.
-
Installation of curb and sidewalk at U Street NW (Friday and Saturday).
SPECIAL NOTICE: 14th St. NW between R St. and S St. NW
Washington Gas had to close 14th St. NW between R St. and S St. NW on September 17th due to a utility issue. This closure was not a part of the 14th Street NW Streetscape project. All lanes are reopened at this time.
![](https://static.wixstatic.com/media/d5aa8e_2b291a499e09497386434bad3f21ff06~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_2b291a499e09497386434bad3f21ff06~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_d50892f3a59e46a78ea0a3cecf175d5d~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_d50892f3a59e46a78ea0a3cecf175d5d~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_4d56ee727c2147d0ad522b13a991d193~mv2_d_4160_2340_s_2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_4d56ee727c2147d0ad522b13a991d193~mv2_d_4160_2340_s_2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f891db76408340d4b43e09b35ebff4ea~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f891db76408340d4b43e09b35ebff4ea~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_2bcce8f6e9ef4ca182277badaa0942f9~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_2bcce8f6e9ef4ca182277badaa0942f9~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f6772b2f97b5491e97face2170eae790~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f6772b2f97b5491e97face2170eae790~mv2.jpg)
Sunday, September 15 – Saturday, September 21, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, September 21st.
![](https://static.wixstatic.com/media/d5aa8e_496560e7742d4dc79c83574fa864d87f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_496560e7742d4dc79c83574fa864d87f~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_e5a367039adc465ba91d3ab9b993aceb~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_e5a367039adc465ba91d3ab9b993aceb~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_85786a1f4cf948679f80177e0b76cd8a~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_85786a1f4cf948679f80177e0b76cd8a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f9ad2835d8f849bb97ef8db336595f4f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f9ad2835d8f849bb97ef8db336595f4f~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_4c34c0a142d04bc3bdeb2d58c6e05662~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_4c34c0a142d04bc3bdeb2d58c6e05662~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f43a760bbbf8409b86919a1084dffcc7~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f43a760bbbf8409b86919a1084dffcc7~mv2.jpg)
Sunday, September 15, 2019
-
No scheduled construction activity.
Monday, September 16 - Saturday, September 21, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Begin electric line on 14th and R Street NW.
-
Pulling of conductor and push buttons at N Street, P Street, Q Street, V Street and W Street NW.
-
Installation of two 20-ft poles and four 28-ft poles for traffic work.
-
Installation of curb and sidewalk at U Street NW (Friday and Saturday).
Sunday, September 8 – Saturday, September 14, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There was no work performed on Saturday, September 14th.
![](https://static.wixstatic.com/media/d5aa8e_b5379ed4bb49452292a54b0fc2999e53~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b5379ed4bb49452292a54b0fc2999e53~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_45958393b9fd449395049e2e369ae4ce~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_45958393b9fd449395049e2e369ae4ce~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_56c723744178402699500d7df6a2d4f8~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_56c723744178402699500d7df6a2d4f8~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_de64a1a685044779918b652769e90c53~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_de64a1a685044779918b652769e90c53~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_065c88ff965248b1ae9201a4df709e49~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_065c88ff965248b1ae9201a4df709e49~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_e15b897ac73840f9964243f64df6630d~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_e15b897ac73840f9964243f64df6630d~mv2.jpg)
Sunday, September 8, 2019
-
No scheduled construction activity.
Monday, September 9 - Friday, September 13, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Excavation for bus island at 14th and R Street NW at the curb parking lane/sidewalk.
-
Removal of existing signs and installation of new signs from Q Street to R Street NW.
-
Saw cuting of existing PCC pavement and preparation of PCC placement including placement of granite curb and brick gutter at the northwest corner of 14th and Florida Avenue NW.
-
Pulling of conductor/push buttons at N Street, P Street, Q Street, V Street W Street and Florida Avenue NW.
Saturday, September 14, 2019
-
No construction activity.
Sunday, September 1 – Saturday, September 7, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, September 7th.
![](https://static.wixstatic.com/media/d5aa8e_7dad9aaf1e234dc48956e25734c8c0d9~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_7dad9aaf1e234dc48956e25734c8c0d9~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_436411dd68a94a97bb2c841f21602f8c~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_436411dd68a94a97bb2c841f21602f8c~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_202c126d98944f02832b64ad86702b98~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_202c126d98944f02832b64ad86702b98~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_dd587219c3104dec90398608657b9605~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_dd587219c3104dec90398608657b9605~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_2df429c7462747e58b2d42cd609014b3~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_2df429c7462747e58b2d42cd609014b3~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_8b7d69ff850f460c8b3c2cea917be3bb~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_8b7d69ff850f460c8b3c2cea917be3bb~mv2.jpg)
Sunday, September 1, 2019
-
No scheduled construction activity.
Monday, September 2, 2019
-
No scheduled construction activity due to the Labor Day Holiday.
Tuesday, September 3 - Friday, September 6, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of bump out and sidewalk from T Street to U Street NW (east side).
-
Installation of curb and sidewalk at W Street and Florida Avenue NW (this work is scheduled to take place on the west side on Friday).
-
Installation of curb and sidewalk at U Street NW (this work is scheduled to take place on Friday).
-
Watermain work at 14th & R Street NW.
-
Shutdown for watermain between T Street and U Street NW (per DC Water scheduled).
-
Pulling of conductor/push buttons at N Street, P Street, Q Street, V Street W Street and Florida Avenue NW.
-
Splicing of manholes from Thomas Circle to Rhode Island Avenue NW.
-
Pulling cable for traffic poles and video detection cameras.
Saturday, September 7, 2019
-
Pulling of conductor/push buttons at N Street, P Street, Q Street, V Street W Street and Florida Avenue NW.
-
Splicing of manholes from Thomas Circle to Rhode Island Avenue NW.
-
Pulling cable for traffic poles and video detection cameras.