SEPTEMBER 2018

Sunday, September 23 – Saturday, September 29, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, September 29th)

Sunday, September 23, 2018

  • No scheduled construction activity.

Monday, September 24, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of handboxes and traffic signal foundations at all corners from N Street to Q Street NW. This activity will be done in a block by block sequence.

Tuesday, September 25, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

  • Installation of handboxes and traffic signal foundations at all corners from N Street to Q Street NW. This activity will be done in a block by block sequence.

Wednesday, September 26, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

  • Installation of handboxes and traffic signal foundations at all corners from N Street to Q Street NW. This activity will be done in a block by block sequence.

Thursday, September 27, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

  • Installation of handboxes and traffic signal foundations at all corners from N Street to Q Street NW. This activity will be done in a block by block sequence.

Friday, September 28, 2018

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

  • Installation of handboxes and traffic signal foundations at all corners from N Street to Q Street NW. This activity will be done in a block by block sequence.

  • Installation of temporary traffic signal cabinet at N Street NW.

Saturday, September 29, 2018

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of handboxes and traffic signal foundations at all corners from N Street to Q Street NW. This activity will be done in a block by block sequence.

  • Installation of temporary traffic signal cabinet at N Street NW.

​Sunday, September 16 – Saturday, September 22, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, September 22nd)

Sunday, September 16, 2018

  • No scheduled construction activity.

Monday, September 17, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).

Tuesday, September 18, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

Wednesday, September 19, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

Thursday, September 20, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

Friday, September 21, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).

  • Correct gutter and curb from Thomas Circle to N Street NW (west side).

Saturday, September 22, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

Sunday, September 9 – Saturday, September 15, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, September 15th)

Sunday, September 9, 2018

  • No scheduled construction activity.

Monday, September 10, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. This work will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).

Tuesday, September 11, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. This work will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).

Wednesday, September 12, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. This work will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

Thursday, September 13, 2018

  • Installation of electrical conduit from Corcoran Street to R Street NW (west side).

  • Installation of traffic signal cabinets from Corcoran Street to R Street NW (west side).

  • Installation of electrical manholes from Corcoran Street to R Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. This work will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

Friday, September 14, 2018

  • Installation of electrical conduit from Corcoran Street to R Street NW (west side).

  • Installation of traffic signal cabinets from Corcoran Street to R Street NW (west side).

  • Installation of electrical manholes from Corcoran Street to R Street NW (west side).

  • ​Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. This work will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

Saturday, September 15, 2018

  • Installation of electrical conduit from Corcoran Street to R Street NW (west side).

  • Installation of traffic signal cabinets from Corcoran Street to R Street NW (west side).

  • Installation of electrical manholes from Corcoran Street to R Street NW (west side).

  • ​Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Removal of streetlight and traffic signal poles from Q Street to U Street NW. This work will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

Sunday, September 2 – Saturday, September 8, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, September 8th)

Sunday, September 2, 2018

  • No scheduled construction activity.

Monday, September 3, 2018

  • No scheduled construction activity due to the Labor Day Holiday.

Tuesday, September 4, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).

Wednesday, September 5, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).​

Thursday, September 6, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).​

Friday, September 7, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of catch basins from Q Street to Corcoran Street NW (west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).

  • Installation of sanitary manholes from N Street to Rhode Island Avenue NW (west side).​

Saturday, September 8, 2018

  • Installation of electrical conduit from Q Street to Corcoran Street NW (west side).

  • Installation of electrical manholes from Q Street to Corcoran Street NW (west side).

  • Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).​