top of page

OCTOBER 2019

Sunday, October 20 – Saturday, October 26, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, October 26th.

Sunday, October 20, 2019

  • No scheduled construction activity.

Monday, October 21 - Friday, October 25, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Excavation and installation of conduits and manhole at R Street NW.

  • Bus island work at R Street NW.

  • Landscaping excavation between Corcoran Street and R Street NW.

  • Placement of granite curb and brick gutter, ramp and sidewalk at Florida Avenue NW.

  • Landscaping between Thomas Circle and Rhode Island Avenue NW.

  • Excavation and installation of electrical conduits at bus island shelter at Florida Avenue NW along with placement of foundation box.

  • Demolition and excavation of pavement at Florida Avenue NW (southwest corner).

​Saturday, October 26, 2019

  • Pulling wires (traffic signal and electric manhole) at S Street and Wallach Place NW.

  • Landscaping operations.

Sunday, October 13 – Saturday, October 19, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, October 19th.

Sunday, October 13, 2019

  • No scheduled construction activity.

Monday, October 14 - Friday, October 18, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of bus island at the southeast corner of T Street NW.

  • Milling and paving from Rhode Island to P Street NW (Thursday and Friday).

  • Installation of inlet at T Street NW (Monday and Tuesday).

  • Work between R Street and P Street NW (conduits, manholes, signal foundations and pressure test).

  • Pulling of conductor and push buttons at N Street and P Street, Q Street, V Street and W Street NW.

  • Installation of two 20-ft poles and four 28-ft poles for traffic work.​

Saturday, October 19, 2019

  • Installation of two 20-ft poles and four 28-ft poles for traffic work.​

Sunday, October 6 – Saturday, October 12, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, October 12th.

Sunday, October 6, 2019

  • No scheduled construction activity.

Monday, October 7 - Friday, October 11, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of bus island at 14th Street and R Street NW.

  • Work on 14th Street and R Street NW to include conduits, manholes, signal foundations and chlorine test.

  • Installation of graded inlet at T Street NW.

  • Pulling of conductor and push buttons at N Street, P Street, Q Street, V Street and W Street NW.

  • Installation of two 20-ft poles and four 28-ft poles for traffic work.​

Saturday, October 12, 2019

  • Installation of two 20-ft poles and four 28-ft poles for traffic work.​

Sunday, September 29 – Saturday, October 5, 2019: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, October 5th.

Sunday, September 29, 2019

  • No scheduled construction activity.

Monday, September 30 - Friday, October 4, 2019

  • Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Transfers from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).

  • Installation of curb and sidewalk at 14th and U Street NW.

  • Installation of bumpout and sidewalk between T Street and U Street NW (east side; Wednesday - Friday).

  • Installation of PCC sidewalk for bus island at the northwest corner of P Street NW (Wednesday - Friday)
  • Installation of bus pad at the southeast corner of P Street NW (Friday).

  • Electric line on 14th and R Street NW.

  • Pulling of conductor and push buttons at N Street, P Street, Q Street, V Street and W Street NW.

  • Installation of two 20-ft poles and four 28-ft poles for traffic work.​

Saturday, October 5, 2019

  • Installation of two 20-ft poles and four 28-ft poles for traffic work.​