OCTOBER 2018
Sunday, October 28 – Saturday, November 3, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, November 3rd)
![](https://static.wixstatic.com/media/d5aa8e_8090f54ee08247d3ab8d1e10d71fbbf1~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_8090f54ee08247d3ab8d1e10d71fbbf1~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_5cc24ccab366427888027ea9c6d34f14~mv2.jpg/v1/fill/w_212,h_212,fp_0.56_0.22,q_90/d5aa8e_5cc24ccab366427888027ea9c6d34f14~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_75fd083d106e4407a8c50b1be60bc176~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_75fd083d106e4407a8c50b1be60bc176~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_ca6abd4ca66b487cae69075039a52f3a~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_ca6abd4ca66b487cae69075039a52f3a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_81c669d7b94d492aaa597a6b4ad7bb5b~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_81c669d7b94d492aaa597a6b4ad7bb5b~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_38abbc4f24ca451795f6b9bef8cecd97~mv2.jpg/v1/fill/w_212,h_212,fp_0.74_0.39,q_90/d5aa8e_38abbc4f24ca451795f6b9bef8cecd97~mv2.jpg)
Sunday, October 28, 2018
-
No scheduled construction activity.
Monday, October 29, 2018 - Friday, November 2, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Demolition and installation of sidewalks from N Street to Rhode Island Avenue NW (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, November 3, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
Sunday, October 21 – Saturday, October 27, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, October 27th)
![](https://static.wixstatic.com/media/d5aa8e_5fbef169395e4ca6a321bf64dbec7d1e~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_5fbef169395e4ca6a321bf64dbec7d1e~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_0645ab463f9c471aaaf89822870ba05a~mv2.jpg/v1/fill/w_212,h_212,fp_0.67_0.3,q_90/d5aa8e_0645ab463f9c471aaaf89822870ba05a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_789c3dce7b074a45b05661b0130f76fc~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_789c3dce7b074a45b05661b0130f76fc~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_e43165a2d1bb4a99a149ddc9b2cc0799~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_e43165a2d1bb4a99a149ddc9b2cc0799~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_94f2852203bf4f7e90933e50399b3afb~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_94f2852203bf4f7e90933e50399b3afb~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_0392781f7d2a465998cc3ace134ef63d~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0392781f7d2a465998cc3ace134ef63d~mv2.jpg)
Sunday, October 21, 2018
-
No scheduled construction activity.
Monday, October 22, 2018
-
Saw cutting bumpouts N Street, Rhode Island Avenue and P Street (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Tuesday, October 23, 2018
-
Saw cutting bumpouts N Street, Rhode Island Avenue and P Street (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Wednesday, October 24, 2018
-
Saw cutting bumpouts N Street, Rhode Island Avenue and P Street (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Thursday, October 25, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Correction of curb and gutter from Thomas Circle to N Street (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Friday, October 26, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Correction of curb and gutter from Thomas Circle to N Street (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, October 27, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Sunday, October 14 – Saturday, October 20, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, October 20th)
![](https://static.wixstatic.com/media/d5aa8e_75660e38e36f4c8d8f656056745635c3~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_75660e38e36f4c8d8f656056745635c3~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_d05f1656f4ac489b8fe06f1bcbe4693a~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_d05f1656f4ac489b8fe06f1bcbe4693a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_484f4647ecb4426d9be76ebeb3119672~mv2.jpg/v1/fill/w_212,h_212,fp_0.09_0.05,q_90/d5aa8e_484f4647ecb4426d9be76ebeb3119672~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_142b130ba2fa4792b90b5927e4bb8482~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_142b130ba2fa4792b90b5927e4bb8482~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_475d60abefb749b3a3ff046b7051abd8~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_475d60abefb749b3a3ff046b7051abd8~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_ef22a0945c264ac9a3f7d0a50d589bd0~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_ef22a0945c264ac9a3f7d0a50d589bd0~mv2.jpg)
Sunday, October 14, 2018
-
No scheduled construction activity.
Monday, October 15, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
Tuesday, October 16, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
Wednesday, October 17, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Correction of curb and gutter from Thomas Circle to N Street (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of 4X4 manhole at R Street NW for mainline.
-
Installation of electrical cables for streetlights from Rhode Island Avene To U Street. This installation will be done in a block by block sequence (east side and west side).
Thursday, October 18, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Correction of curb and gutter from Thomas Circle to N Street (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of 4X4 manhole at R Street NW for mainline.
-
Installation of electrical cables for streetlights from Rhode Island Avene To U Street. This installation will be done in a block by block sequence (east side and west side).
Friday, October 19, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Correction of curb and gutter from Thomas Circle to N Street (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of 4X4 manhole at R Street NW for mainline.
-
Installation of electrical cables for streetlights from Rhode Island Avene To U Street. This installation will be done in a block by block sequence (east side and west side).
Saturday, October 20, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Sunday, October 7 – Saturday, October 13, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, October 13th)
![](https://static.wixstatic.com/media/d5aa8e_db63fd46b83a483889c9e716387d4cd3~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_db63fd46b83a483889c9e716387d4cd3~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a496901976434a5ab27fdd002b01355a~mv2.jpg/v1/fill/w_212,h_212,fp_0.11_0.41,q_90/d5aa8e_a496901976434a5ab27fdd002b01355a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_c35f54f6f3b242e39d1709603f721f23~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_c35f54f6f3b242e39d1709603f721f23~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_3c43187573dc472d9d3d1450aeba540c~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_3c43187573dc472d9d3d1450aeba540c~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_fce997295e2a424db77058e5160697a9~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_fce997295e2a424db77058e5160697a9~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_7d7ea8519c0f48e1b939c4239c60e959~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_7d7ea8519c0f48e1b939c4239c60e959~mv2.jpg)
Sunday, October 7, 2018
-
No scheduled construction activity.
Monday, October 8, 2018
-
No construction activity scheduled due to the Columbus Day holiday.
Tuesday, October 9, 2018
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
Wednesday, October 10, 2018
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Correct gutter and curb from Thomas Circle to N Street NW (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
Thursday, October 11, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Correct gutter and curb from Thomas Circle to N Street NW (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
Friday, October 12, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree removals from Thomas Circle to Q Street NW (east and west side).
-
Correct gutter and curb from Thomas Circle to N Street NW (west side).
-
Installation of electrical conduit and manholes from Florida Avenue to W Street NW (west side).
Saturday, October 13, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Sunday, September 30 – Saturday, October 6, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, October 6th)
![](https://static.wixstatic.com/media/d5aa8e_0877914f67924836b612227325affd62~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0877914f67924836b612227325affd62~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f8f6d5b20ab54e3c8ec4c0d9433653f7~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f8f6d5b20ab54e3c8ec4c0d9433653f7~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_0e2de39c8da242cba16cc32cea79249e~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0e2de39c8da242cba16cc32cea79249e~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f6f8fee31ad245cdb083e777f23b1b96~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f6f8fee31ad245cdb083e777f23b1b96~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_97afa60196fa4722818e58513106b4f7~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_97afa60196fa4722818e58513106b4f7~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_59fcc2c0a83d45719f713ecd73951cfd~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_59fcc2c0a83d45719f713ecd73951cfd~mv2.jpg)
Sunday, September 30, 2018
-
No scheduled construction activity.
Monday, October 1, 2018
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree Removal from Thomas Circle to Q Street NW (east and west side).
Tuesday, October 2, 2018
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree Removal from Thomas Circle to Q Street NW (east and west side).
-
Correct curb and gutter from Thomas Circle to N Street (west side).
Wednesday, October 3, 2018
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree Removal from Thomas Circle to Q Street NW (east and west side).
-
Correct curb and gutter from Thomas Circle to N Street (west side).
Thursday, October 4, 2018
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree Removal from Thomas Circle to Q Street NW (east and west side).
-
Correct curb and gutter from Thomas Circle to N Street (west side).
Friday, October 5, 2018
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Tree Removal from Thomas Circle to Q Street NW (east and west side).
-
Correct curb and gutter from Thomas Circle to N Street (west side).
Saturday, October 6, 2018
-
Installation of catch basins from Q Street to Corcoran Street NW (west side).
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).