MAY 2019
Sunday, May 26 – Saturday, June 1, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, June 1st.
Sunday, May 26, 2019
-
No scheduled construction activity.
Monday, May 27 - Friday, May 31, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of curb and sidewalk from 14th & U Street toward 14th & Florida Avenue NW.
-
Installation of fire hydrants at S Street NW.
-
Installation of catch basins at 14th & S Street NW (scheduled to take place on Friday).
-
Installation of streetlight and traffic signal foundations at S Street, T Street and Florida Avenue NW.
-
Reconnecting for water service at T Street to U Street NW (west side).
-
Shutdown of watermain between 14th Street and T Street NW (per DC Water's schedule).
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
-
Tree trimming at the southwest corner of Florida Avenue and Rhode Island Avenue NW (scheduled to take place on Wednesday).
-
Installation of traffic control cabinets at S Street, T Street and Florida Avenue NW.
Saturday, June 1, 2019
-
No scheduled construction activity.
Sunday, May 19 – Saturday, May 25, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, May 25th.
![](https://static.wixstatic.com/media/d5aa8e_6cb41a4eaf8d47a58e09577d7e2e34f7~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_6cb41a4eaf8d47a58e09577d7e2e34f7~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_57417483ecf8412b85bc9a024fe5e201~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_57417483ecf8412b85bc9a024fe5e201~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_d7f25689b8ae4325bcea03ff38ef2e32~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_d7f25689b8ae4325bcea03ff38ef2e32~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_eca674cba6274491bd2aa37d3fc0ce8d~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_eca674cba6274491bd2aa37d3fc0ce8d~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_412eec1d65594ca4bd7cdf830ac5d9aa~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_412eec1d65594ca4bd7cdf830ac5d9aa~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_3f11b49e794b4c34883f42d88bb42767~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_3f11b49e794b4c34883f42d88bb42767~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_c14e8703616e4c199f1f3196a6206d25~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_c14e8703616e4c199f1f3196a6206d25~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_d12c3f52da844c0599b4778b0fbf79f0~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_d12c3f52da844c0599b4778b0fbf79f0~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_bafa8066c3464b3881e742409f35fa3f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_bafa8066c3464b3881e742409f35fa3f~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_e820fdea78264ab7850e6e9cf8f193b0~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_e820fdea78264ab7850e6e9cf8f193b0~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_b62ef40df0144359a0cb15f475138d53~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b62ef40df0144359a0cb15f475138d53~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_6bb3f740b061400aae5fc556129ddebd~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_6bb3f740b061400aae5fc556129ddebd~mv2.jpg)
Sunday, May 19, 2019
-
No scheduled construction activity.
Monday, May 20 - Friday, May 24, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of curb and sidewalk from 14th & U Street toward 14th & Florida Avenue NW.
-
Installation of fire hydrants at S Street NW.
-
Installation of streetlight and traffic signal foundations at S Street, T Street and Florida Avenue NW.
-
Installation of catch basins at T Street NW (southwest corners).
-
Reconnecting for water service at T Street to U Street NW (west side).
-
Shutdown of watermain between 14th Street and T Street NW (per DC Water's schedule).
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
-
Tree trimming at the southwest corner of Florida Avenue and Rhode Island Avenue NW (scheduled to take place on Monday and Wednesday).
-
Installation of foundations and traffic control cabinets at S Street, T Street and Florida Avenue NW.
Saturday, May 25, 2019
-
No scheduled construction activity due to the Memorial Day holiday weekend.
Sunday, May 12 – Saturday, May 18, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, May 18th.
Sunday, May 12, 2019
-
No scheduled construction activity.
Monday, May 13 - Wednesday, May 15, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrants at W Street, V Street and S Street NW.
-
Reconnecting for water service at Swann Street to U Street (west side).
-
Installation of foundations and traffic control cabinets at S Street, T Street, U Street and Florida Avenue NW.
-
Installation of the curb and sidewalk at 14th and U Street NW (NW corner).
-
Installation of the TEC foundation and cabinet at the SE corner of U Street NW.
Thursday, May 16, 2019 - Saturday, May 18, 2019
-
All of the above activities with the exception of the installation of TEC foundation and cabinet at the SE corner of U Street NW. Additional work to be completed: installation of curb and sidewalk from U Street to V Street NW (east side).
Sunday, May 5 – Saturday, May 11, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, May 11th.
Sunday, May 5, 2019
-
No scheduled construction activity.
Monday, May 6 - Wednesday, May 8, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrants at W Street, V Street and S Street NW.
-
Reconnecting for water service from Swann Street to U Street (west side).
-
Installation of foundations and traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of Traffic Control cabinets at R Street, S Street, T Street and Florida Avenue NW.
-
Installation of the curb and sidewalk at 14th and U Street NW (NW corner).
-
Installation of three grate vaults between N Street and Rhode Island NW (east side).
-
Installation of the TEC foundation and cabinet at the SE corner of U Street NW.
Thursday, May 9, 2019 - Saturday, May 11, 2019
-
All of the above activities with the exception of the installation of curb and sidewalk at 14th and U Street NW (NW corner) and the installation of three grate vaults between N Street and Rhode Island Avenue NW. Additional work to be completed: installation of curb and sidewalk from U Street to V Street NW (east side).