JULY 2019
Sunday, July 28 – Saturday, August 3, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, August 3rd.
![](https://static.wixstatic.com/media/d5aa8e_069c4a72b7424032a7ff79a8ce5a11b9~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_069c4a72b7424032a7ff79a8ce5a11b9~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_b2fa9fe7868048c0bf4446207f29dd35~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b2fa9fe7868048c0bf4446207f29dd35~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_1860dceebf59413281e5846eb4d53a9d~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_1860dceebf59413281e5846eb4d53a9d~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f26ccc9e47bc4dd8a0d50254f71a6cfd~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f26ccc9e47bc4dd8a0d50254f71a6cfd~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_471e9fafd426469893282a6adbcc3b7f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_471e9fafd426469893282a6adbcc3b7f~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_6e8a79b50546412ea1cef1998d291821~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_6e8a79b50546412ea1cef1998d291821~mv2.jpg)
Sunday, July 28, 2019
-
No scheduled construction activity.
Monday, July 29 - Friday, August 2, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of bump out, curb and sidewalk from T Street to Wallach Place NW (east side).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Shutdown for watermain between T & U Street NW (per DC Water's schedule).
-
Installation of bus island at 14th & U Street NW.
-
Mill and overlay (Thomas Circle to Rhode Island Avenue NW.
-
Pulling cable for traffic poles and video detection cameras.
-
Tree removal at the southewest corner of Rhode Island Avenue NW.
-
Tree removal at the southeast corner of T Street NW.
Saturday, August 3, 2019
-
Installation of bus island at 14th & U Street NW.
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
-
Milling and overlay.
-
Pulling cable for traffic poles and video detection cameras.
Sunday, July 21 – Saturday, July 27, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, July 27th.
![](https://static.wixstatic.com/media/d5aa8e_ac84029efcf549bead62f9c438871b0e~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_ac84029efcf549bead62f9c438871b0e~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a2c2c9ade2ca4e21a87b2ea0d023d161~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a2c2c9ade2ca4e21a87b2ea0d023d161~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_43795b283ef54606997b3ba73940465a~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_43795b283ef54606997b3ba73940465a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_66053b03ad254d208e5be754c5f8fe51~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_66053b03ad254d208e5be754c5f8fe51~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_ac4f5c501e894548997235e3e0f2fad1~mv2.png/v1/fill/w_212,h_212,q_90/d5aa8e_ac4f5c501e894548997235e3e0f2fad1~mv2.png)
![](https://static.wixstatic.com/media/d5aa8e_13b4bc4f06804540966c17c1a77c6ffd~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_13b4bc4f06804540966c17c1a77c6ffd~mv2.jpg)
Sunday, July 21, 2019
-
No scheduled construction activity.
Monday, July 22 - Friday, July 26, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of bump out, curb and sidewalk from T Street to Wallach Place NW (east side).
-
Installation of curb and sidewalk from Wallach Place to U Street NW (east side).
-
Installation of bus island at 14th & P Street NW (west side).
-
Installation of bus island at 14th & U Street NW (both east and west side).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Shutdown for watermain between T & U Street NW (per DC Water's schedule).
-
Tree removal at the southewest corner of Rhode Island Avenue NW.
-
Tree removal at the southeast corner of T Street NW.
Saturday, July 27, 2019
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
-
Pulling cable for traffic poles and video detection cameras.
Sunday, July 14 – Saturday, July 20, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, July 20th.
![](https://static.wixstatic.com/media/d5aa8e_f8e879ec2d734ef1adf690783f955c43~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f8e879ec2d734ef1adf690783f955c43~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_b01d026368374e85bc3c1c30448a1d3b~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b01d026368374e85bc3c1c30448a1d3b~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_7fe2bdb5510149fcabd65795dcc84b9a~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_7fe2bdb5510149fcabd65795dcc84b9a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_37179ebe30c5452c9d1d08d6c41f1b69~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_37179ebe30c5452c9d1d08d6c41f1b69~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f56f3e6b05494205b8c549533a89d4a4~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f56f3e6b05494205b8c549533a89d4a4~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_49ab5b749c6b4fe6836fc96f34db6dcc~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_49ab5b749c6b4fe6836fc96f34db6dcc~mv2.jpg)
Sunday, July 14, 2019
-
No scheduled construction activity.
Monday, July 15 - Friday, July 19, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of bump out, curb and sidewalk from T Street to Wallach Street NW (east side).
-
Installation of bus island at 14th & P Street NW (east side).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Shutdown for watermain between T & U Street NW (per DC Water's schedule).
-
Tree trimming at the southwest corner of Rhode Island Avenue NW.
-
Tree removal at the southeast corner of T Street NW.
Saturday, July 20, 2019
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
-
Pulling cable for traffic poles and video detection cameras.
Sunday, July 7 – Saturday, July 13, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, June 13th.
![](https://static.wixstatic.com/media/d5aa8e_8d690a9406fa43fb90ffcdc5e181c711~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_8d690a9406fa43fb90ffcdc5e181c711~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a9acde4651664b87b31d3a3ac93f7558~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a9acde4651664b87b31d3a3ac93f7558~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a2c499700380499c817e1da5322257e0~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a2c499700380499c817e1da5322257e0~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_101ad07f27894257a3951ccd3e639d8d~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_101ad07f27894257a3951ccd3e639d8d~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_7d788f6ad80f4c95ae194f769c8effd2~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_7d788f6ad80f4c95ae194f769c8effd2~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_c19a3fdab566410484101724a158a778~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_c19a3fdab566410484101724a158a778~mv2.jpg)
Sunday, July 7, 2019
-
No scheduled construction activity.
Monday, July 8 - Friday, July 12, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of curb and sidewalk from S Street to T Street NW (east side).
-
Installation of bus island at 14th & Rhode Island Avenue NW (west side).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
Saturday, July 13, 2019
-
No scheduled construction activity.
Sunday, June 30 – Saturday, July 6, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, July 6th.
![](https://static.wixstatic.com/media/d5aa8e_77f38869d5124f48b290a1f716dfffbb~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_77f38869d5124f48b290a1f716dfffbb~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a09117b7ca8543f09c02c17123babd0a~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a09117b7ca8543f09c02c17123babd0a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_d98ebbe728554b108ba5c5e5b09b0b0e~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_d98ebbe728554b108ba5c5e5b09b0b0e~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_2ba72408f926402d85c4df9b455a84c7~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_2ba72408f926402d85c4df9b455a84c7~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_6826488c6f9d432db6115cb868fee017~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_6826488c6f9d432db6115cb868fee017~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_e87fc22c430e4f5abc0ceb6b1e5c90a6~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_e87fc22c430e4f5abc0ceb6b1e5c90a6~mv2.jpg)
Sunday, June 30, 2019
-
No scheduled construction activity.
Monday, July 1 - Wednesday, July 3, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of curb and sidewalk from S Street to T Street NW (east side).
-
Installation of bus island at 14th & Rhode Island Avenue NW (west side).
-
Installation of additional 4X4 manhole via RFI at 14th & R Street NW.
-
Installation of streetlight and traffic signal foundations at S Street and T Street NW.
-
Watermain work at 14th & R Street NW.
-
Shutdown for watermain between 14th & T Street NW (per DC Water's schedule).
-
Installation of bolt-on UPS systems at traffic control cabinets from N Street to W Street NW.
Thursday, July 4, 2019
-
No scheduled construction activity due to the Independence Day Holiday.
Friday, July 5, 2019
-
Continuation of the same activities listed for the period of July 1 - July 3.
Saturday, July 6, 2019
-
Pulling electrical cable.