top of page

JULY 2018

Sunday, July 29 – Saturday, August 4, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, August 4th)

Sunday, July 29, 2018
  • No scheduled construction activity.

Monday, July 30, 2018

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Tuesday, July 31, 2018

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Wednesday, August 1, 2018

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Thursday, August 2, 2018

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Friday, August 3, 2018

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Saturday, August 4, 2018

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Sunday, July 22 – Saturday, July 28, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, July 28th)

Sunday, July 22, 2018
  • No scheduled construction activity.

Monday, July 23, 2018

  • Installation of manhole and catch basins. 

Tuesday, July 24, 2018

  • Installation of manhole and catch basins.

Wednesday, July 25, 2018

  • Installation of manhole and catch basins.

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Thursday, July 26, 2018

  • Installation of manhole and catch basins.

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Friday, July 27, 2018

  • Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Saturday, July 28, 2018

  • ​Installation of handbox, traffic cabinet, manholes and catch basins from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Sunday, July 15 – Saturday, July 21, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, July 21st)

Sunday, July 15, 2018
  • No scheduled construction activity.

Monday, July 16, 2018

  • Installation of a manhole and catch basins north of P Street NW; installation of catch basin south of P Street NW.

Tuesday, July 17, 2018

  • Installation of a manhole and catch basins north of P Street NW; installation of catch basin south of P Street NW.

Wednesday, July 18, 2018

  • Installation of a manhole and catch basins north of P Street NW; installation of catch basin south of P Street NW.

  • Installation of handbox (HB01), traffic cabinet and manholes from N Street to Rhode Island Avenue NW (west side).

  • Installation of catch basins and manhole from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Thursday, July 19, 2018

  • Installation of a manhole and catch basins north of P Street NW; installation of catch basin south of P Street NW.

  • Installation of handbox (HB01), traffic cabinet and manholes from N Street to Rhode Island Avenue NW (west side).

  • Installation of catch basins and manhole from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Friday, July 20, 2018

  • Installation of handbox (HB01), traffic cabinet and manholes from N Street to Rhode Island Avenue NW (west side).

  • Installation of catch basins and manhole from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Saturday, July 21, 2018

  • Installation of handbox (HB01), traffic cabinet and manholes from N Street to Rhode Island Avenue NW (west side).

  • Installation of catch basins and manhole from N Street to Rhode Island Avenue NW (west side).

  • Installation of electrical conduit from Thomas Circle to N Street NW (west side).

Sunday, July 8 – Saturday, July 14, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, July 14th)

Sunday, July 8, 2018
  • No scheduled construction activity.

Monday, July 9, 2018

  • Installation of catch basins from P Street to Q Street NW (east side).

  • Installation of street light foundations from P Street to Q Street NW (east side).

  • Installation of 4x4x4 manhole at R Street NW (east side).

  • Installation of foundation for traffic signal cabinet at R Street Street NW (east side).

Tuesday, July 10, 2018

  • Installation of catch basins from P Street to Q Street NW (east side).

  • Installation of street light foundations from P Street to Q Street NW (east side).

  • Installation of 4x4x4 manhole at R Street NW (east side).

  • Installation of foundation for traffic signal cabinet at R Street Street NW (east side).

Wednesday, July 11, 2018

  • Installation of catch basins from P Street to Q Street NW (east side).

  • Installation of street light foundations from P Street to Q Street NW (east side).

  • Installation of 4x4x4 manhole at R Street NW (east side).

  • Installation of foundation for traffic signal cabinet at R Street Street NW (east side).

Thursday, July 12, 2018

  • Installation of street light foundations from P Street to Q Street NW (east side).

Friday, July 13, 2018

  • Installation of street light foundations from P Street to Q Street NW (east side).​

Saturday, July 14, 2018

  • No scheduled construction activity.

Sunday, July 1 – Saturday, July 7, 2018: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, July 7th)

Sunday, July 1, 2018
  • No scheduled construction activity.

Monday, July 2, 2018

  • Saw cutting and excavation for electrical conduit from T Street to Wallach Street NW (northbound lane).

  • Installation of traffic signal cabinet foundations (TC4, TC5).

  • Installation of Handbox (HB03) at the corner of N Street NW (east side).

Tuesday, July 3, 2018

  • Saw cutting and excavation for electrical conduit from T Street to Wallach Street NW (northbound lane).

  • Saw cutting and excavation for electrical conduit from Wallach Street to V Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from P Street to Q Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at Q Street NW (east side).

  • Installation of foundation for traffic signal cabinet at Rhode Island Avenue NW (east side).

  • Installation of foundation for traffic signal cabinet at P Street NW (east side).

  • Installation of foundation for traffic signal cabinet at Q Street NW (east side).

  • Installation of conduits (from MH40 to L53A).

  • Installation of traffic signal cabinet foundations (TC4, TC5).

  • Installation of Handbox (HB03) at the corner of N Street NW (east side).

Wednesday, July 4, 2018

  • No scheduled construction activity (Independence Day Holiday).

Thursday, July 5, 2018

  • Saw cutting and excavation for electrical conduit from T Street to Wallach Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from P Street to Q Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at Q Street NW (east side).

  • Installation of foundation for traffic signal cabinet at Rhode Island Avenue NW (east side).

  • Installation of foundation for traffic signal cabinet at P Street NW (east side).

  • Installation of foundation for traffic signal cabinet at R Street NW (east side).

  • Installation of conduits (from MH40 to L53A).

  • Installation of traffic signal cabinet foundations (TC4, TC5).

  • Installation of Handbox (HB03) at the corner of N Street NW (east side).

Friday, July 6, 2018

  • Saw cutting and excavation for electrical conduit from T Street to Wallach Street NW (northbound lane).

  • Demolition and installation of sidewalk from Rhode Island Avenue to P Street NW (east side).

  • Demolition of existing curb & gutter from Rhode Island Avenue to P Street NW (east side).

  • Installation of streetlight foundations from P Street to Q Street NW (east side).

  • Installation of traffic signal pole on temporary foundation at Q Street NW (east side).

  • Installation of foundation for traffic signal cabinet at Rhode Island Avenue NW (east side).

  • Installation of foundation for traffic signal cabinet at P Street NW (east side).

  • Installation of foundation for traffic signal cabinet at R Street NW (east side).

  • Installation of conduits (from MH40 to L53A).

  • Installation of traffic signal cabinet foundations (TC4, TC5).

  • Installation of Handbox (HB03) at the corner of N Street NW (east side).

Saturday, July 7, 2018

  • No scheduled construction activity.

DCMayorLogo_White-web.png

© 2020 DDOT

Terms of Service

bottom of page