JANUARY 2020

Sunday, January 26 – Saturday, February 1, 2020: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, February 1st.

Sunday, January 26, 2020

  • No scheduled construction activity.

Monday, January 27 - Friday, January 31, 2020

  • Preparation for water line tie-in at R Street NW.

  • Installation of traffic signals and pedestrian signals at T Street NW.

  • Excavation of asphalt roadway for water valve location at Q Street NW.

  • Excavation and installation of conduit for the hand box at the bus stop at R Street NW.

  • Demolition of sidewalk at Florida Avenue NW for connections to Pepco feeder vault and manhole.

  • Removal of permeable paver sidewalk for installation of geo grid at various locations within the 1300 and 1400 block of 14th Street NW.

Saturday, February 1, 2020

  • Installation of pedestrian signals, LED modules and signal heads at T Street NW.

  • Removal of temporary concrete bases and poles at W Street NW.

Sunday, January 12 – Saturday, January 18, 2020: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, January 18th.

Sunday, January 12, 2020

  • No scheduled construction activity.

Monday, January 13 - Friday, January 17, 2020

  • Work on bus islands at 14th and R Street NW (southbound). 

  • Base repair at 14th and R Street NW.

  • Curb and sidewalk work at 14th and T Street NW.

  • Landscaping work being completed along the corridor. 

  • installation of fiber into the Reeves Building.

  • Installation of light fixtures.

Saturday, January 18, 2020

  • Installation of fiber splicing.

Sunday, January 5 – Saturday, January 11, 2020: 
Scheduled Activity, Weather Permitting 

(PENDING: There is no work currently scheduled for Saturday, January 11th.

Sunday, January 5, 2020

  • No scheduled construction activity.

Monday, January 6 - Friday, January 10, 2020

  • Water tie-in at 14th and R Street NW (per DC Water's Schedule). Please note: this work is being performed overnight (Monday) to minimize the impacts of the water shut-off necessary to complete this activity.

 

Saturday, January 11, 2020

  • No scheduled construction activity.

Sunday, December 29 – Saturday, January 4, 2020: 
Scheduled Activity, Weather Permitting 

(PENDING: There is work currently scheduled for Saturday, January 4th.

Sunday, December 29, 2020

  • No scheduled construction activity.

Monday, December 30 and Tuesday, December 31, 2020

  • Bench Installation.

  • Removal of existing trash receptacles from R Street to Florida Avenue NW.

  • Excavation for signal and light pole foundation at T Street NW.

  • Installation of cable and wiring new traffic cabinet at Q Street NW.

  • Concrete work on bus island at R Street NW.

Wednesday, January 1, 2020

  • No construction activity due to the New Year's Day Holiday.

Thursday, January 2 - Friday, January 3, 2020

  • Installation of traffic signal pole foundation at Florida Avenue NW.

  • Installation of pendant poles and teardrop fixtures at Wallach Place NW.

  • Installation of granite curb for bus island at Florida Avenue NW.

  • Installation of conduit between the proposed manhole and foot light pole foundation at T Street NW.

  • Placed cold patch asphalt to restore the sidewalk over the pipe trenches for the traffic signal/light poles on the corner of T Street NW.

  • Installation of the inlet top on the storm drainage structure at the southwest corner of T Street NW.

  • Installation of porous flexible pavement.

  • Installation hand box at the southeast corner of Florida Avenue NW.

Saturday, January 4, 2020

  • Work on catch basins from N Street to T Street NW.

bottom of page