Sunday, January 26 – Saturday, February 1, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, February 1st.
Sunday, January 26, 2020
-
No scheduled construction activity.
Monday, January 27 - Friday, January 31, 2020
-
Preparation for water line tie-in at R Street NW.
-
Installation of traffic signals and pedestrian signals at T Street NW.
-
Excavation of asphalt roadway for water valve location at Q Street NW.
-
Excavation and installation of conduit for the hand box at the bus stop at R Street NW.
-
Demolition of sidewalk at Florida Avenue NW for connections to Pepco feeder vault and manhole.
-
Removal of permeable paver sidewalk for installation of geo grid at various locations within the 1300 and 1400 block of 14th Street NW.
Saturday, February 1, 2020
-
Installation of pedestrian signals, LED modules and signal heads at T Street NW.
-
Removal of temporary concrete bases and poles at W Street NW.
Sunday, January 12 – Saturday, January 18, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, January 18th.
Sunday, January 12, 2020
-
No scheduled construction activity.
Monday, January 13 - Friday, January 17, 2020
-
Work on bus islands at 14th and R Street NW (southbound).
-
Base repair at 14th and R Street NW.
-
Curb and sidewalk work at 14th and T Street NW.
-
Landscaping work being completed along the corridor.
-
installation of fiber into the Reeves Building.
-
Installation of light fixtures.
Saturday, January 18, 2020
-
Installation of fiber splicing.
Sunday, January 5 – Saturday, January 11, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, January 11th.
Sunday, January 5, 2020
-
No scheduled construction activity.
Monday, January 6 - Friday, January 10, 2020
-
Water tie-in at 14th and R Street NW (per DC Water's Schedule). Please note: this work is being performed overnight (Monday) to minimize the impacts of the water shut-off necessary to complete this activity.
Saturday, January 11, 2020
-
No scheduled construction activity.
Sunday, December 29 – Saturday, January 4, 2020:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, January 4th.
Sunday, December 29, 2020
-
No scheduled construction activity.
Monday, December 30 and Tuesday, December 31, 2020
-
Bench Installation.
-
Removal of existing trash receptacles from R Street to Florida Avenue NW.
-
Excavation for signal and light pole foundation at T Street NW.
-
Installation of cable and wiring new traffic cabinet at Q Street NW.
-
Concrete work on bus island at R Street NW.
Wednesday, January 1, 2020
-
No construction activity due to the New Year's Day Holiday.
Thursday, January 2 - Friday, January 3, 2020
-
Installation of traffic signal pole foundation at Florida Avenue NW.
-
Installation of pendant poles and teardrop fixtures at Wallach Place NW.
-
Installation of granite curb for bus island at Florida Avenue NW.
-
Installation of conduit between the proposed manhole and foot light pole foundation at T Street NW.
-
Placed cold patch asphalt to restore the sidewalk over the pipe trenches for the traffic signal/light poles on the corner of T Street NW.
-
Installation of the inlet top on the storm drainage structure at the southwest corner of T Street NW.
-
Installation of porous flexible pavement.
-
Installation hand box at the southeast corner of Florida Avenue NW.
Saturday, January 4, 2020
-
Work on catch basins from N Street to T Street NW.