FEBRUARY 2019
Sunday, February 24 – Saturday, March 2, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, March 2nd)
![](https://static.wixstatic.com/media/d5aa8e_753a7c067a2e4ecfb33daed3ee76642b~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_753a7c067a2e4ecfb33daed3ee76642b~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_6299142c900b4be29879d7d2b631c0cb~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_6299142c900b4be29879d7d2b631c0cb~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_24afd75194b24b00a4142ed601b430cc~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_24afd75194b24b00a4142ed601b430cc~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a670ac6d86ab4b44827f427e170d3462~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a670ac6d86ab4b44827f427e170d3462~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_0adf9ddf29b84bdbac5a9df3d8efd375~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0adf9ddf29b84bdbac5a9df3d8efd375~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_0e6fd9da24e14539983416016d294150~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0e6fd9da24e14539983416016d294150~mv2.jpg)
Sunday, February 24, 2019
-
No scheduled construction activity.
Monday, February 25 - Friday, March 1, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from P Street to R Street NW (west side).
-
Installation of electrical conduit and manholes at U Street NW (east and west side).
-
Installation of fire hydrant at S Street NW, Church Street NW and Florida Avenue NW.
-
Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at W Street, R Street, S Street, T Street and Florida Avenue NW.
-
Installation of foundation and TEC cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, March 2, 2019
-
All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.
-
Additional activity: Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Sunday, February 17 – Saturday, February 23, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, February 23rd)
![](https://static.wixstatic.com/media/d5aa8e_70157dc75a9b480b83d747037cc9c2be~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_70157dc75a9b480b83d747037cc9c2be~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a12379f87c6546a895414ad420a935e8~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a12379f87c6546a895414ad420a935e8~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f67825d2d863484a94fbf8e58934a862~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f67825d2d863484a94fbf8e58934a862~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_56e1b700200f4d9fba8e12312ed6e49c~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_56e1b700200f4d9fba8e12312ed6e49c~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_7b73312d421641dab10b41ccf04f4362~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_7b73312d421641dab10b41ccf04f4362~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_8ddf05d09fc94535a9968852b4c4dc7b~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_8ddf05d09fc94535a9968852b4c4dc7b~mv2.jpg)
Sunday, February 17, 2019
-
No scheduled construction activity.
Monday, February 18, 2019
-
No scheduled construction activity due to the President's Day Holiday.
Tuesday, February 19 - Friday, February 22, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from P Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from P Street to R Street NW (west side).
-
Installation of electrical conduit and manholes at U Street NW (east and west side).
-
Installation of fire hydrant at S Street NW, T Street, Church Street and Swann Street NW.
-
Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at W Street, R Street, S Street, T Street and Florida Avenue NW.
-
Installation of foundation and TEC cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, February 23, 2019
-
All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.
-
Additional activity: Installation of electrical cable for streetlights from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Sunday, February 10 – Saturday, February 16, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, February 16th)
![](https://static.wixstatic.com/media/d5aa8e_3d02abb39e644636906e787f15a443db~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_3d02abb39e644636906e787f15a443db~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_facfb1527050419baf0863507a478ee9~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_facfb1527050419baf0863507a478ee9~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a8f58733e23c44a09086a73f8a873f49~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a8f58733e23c44a09086a73f8a873f49~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_ae27e6036410415a864f124f5f701712~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_ae27e6036410415a864f124f5f701712~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a7a5736f86964b3f8be5b0ca6e9a7ca6~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a7a5736f86964b3f8be5b0ca6e9a7ca6~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_1c43323afec9426bb4bf0a272641e1c6~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_1c43323afec9426bb4bf0a272641e1c6~mv2.jpg)
Sunday, February 10, 2019
-
No scheduled construction activity.
Monday, February 11 - Friday, February 15, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from P Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from P Street to R Street NW (west side).
-
Installation of electrical conduit and manholes at U Street NW (east and west side).
-
Installation of fire hydrant at S Street NW, T Street NW, Church Street NW and Swann Street NW.
-
Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at W Street, R Street, S Street, T Street and Florida Avenue NW.
-
Installation of foundation and TEC cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, February 16, 2019
-
All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.
Sunday, February 3 – Saturday, February 9, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, February 9th)
![](https://static.wixstatic.com/media/d5aa8e_bce468d58ac3424389a0b91194d65a4e~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_bce468d58ac3424389a0b91194d65a4e~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_617dbf69ba90472c8b661ae5178a70ea~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_617dbf69ba90472c8b661ae5178a70ea~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_760f3c0cdcf44c00980beac78ba3dfd4~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_760f3c0cdcf44c00980beac78ba3dfd4~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_b081a02f53da497090d79f7803d2b054~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b081a02f53da497090d79f7803d2b054~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a7b2515d0531481ab1b2ef717ba87b16~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a7b2515d0531481ab1b2ef717ba87b16~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_db5dd304c41c4023815eafd77add416f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_db5dd304c41c4023815eafd77add416f~mv2.jpg)
Sunday, February 3, 2019
-
No scheduled construction activity.
Monday, February 4 - Friday, February 8, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from P Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from Q Street to R Street NW (east side).
-
Installation of electrical conduit and manholes at U Street NW (east and west side).
-
Installation of fire hydrant at S Street NW, T Street NW, Church Street NW and Swann Street NW.
-
Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at N Street, P Street, W Street, Wallach Place and Rhode Island Avenue NW.
-
Installation of foundation and TEC cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from U Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, February 9, 2019
-
All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.