DECEMBER 2018
Sunday, December 23 – Saturday, December 29, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, December 29th)
Sunday, December 23, 2018
-
No scheduled construction activity.
Monday, December 24, 2018 - Tuesday, December 25, 2018
-
No scheduled construction activity due to Christmas Holiday.
Wednesday, December 26, 2018 - Friday, December 28, 2018
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from P Street to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from P Street to Q Street NW (east side).
-
Installation of electrical conduit and manholes from W Street to V Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of TEC cabinet at the southeast corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from U Street to V Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, December 29, 2018
-
No scheduled construction activity.
Sunday, December 16 – Saturday, December 22, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is no work currently scheduled for Saturday, December 22nd)
![](https://static.wixstatic.com/media/d5aa8e_650abb1289ac48f39bcba29ac55c17ec~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_650abb1289ac48f39bcba29ac55c17ec~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_6fce5fa07777406b911ea86f4d3c02be~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_6fce5fa07777406b911ea86f4d3c02be~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_b3064f6a57424ac28c8db329c4438458~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b3064f6a57424ac28c8db329c4438458~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_d4a64887abb34f0abc26405e8f8a49d4~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_d4a64887abb34f0abc26405e8f8a49d4~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_3276bf5cf8e04ff69d62698b96dd5b91~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_3276bf5cf8e04ff69d62698b96dd5b91~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_c0a4408f9d5948d299aab68df4fb696c~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_c0a4408f9d5948d299aab68df4fb696c~mv2.jpg)
Sunday, December 16, 2018
-
No scheduled construction activity.
Monday, December 17, 2018 - Friday, December 21, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Rhode Island Avenue to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from P Street to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from P Street to Q Street NW (east side).
-
Installation of electrical conduit and manholes from W Street to V Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of foundation and TEC cabinet at the southeast corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from U Street to W Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, December 22, 2018
-
No scheduled construction activity.
Sunday, December 9 – Saturday, December 15, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, December 15th)
![](https://static.wixstatic.com/media/d5aa8e_4b2659fddaf74b6ea0d3144e76c8a07e~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_4b2659fddaf74b6ea0d3144e76c8a07e~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_01fdbfe893e5490eb8bd298ae27426ec~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_01fdbfe893e5490eb8bd298ae27426ec~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_7a13beb841054164854ea254eaf76a13~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_7a13beb841054164854ea254eaf76a13~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_4177c923754e41618bfa929406646b05~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_4177c923754e41618bfa929406646b05~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_fa7565be7fb7448aa8abdfb6e3cdffea~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_fa7565be7fb7448aa8abdfb6e3cdffea~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a8c579e7f0464f2084e78b76285593d6~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a8c579e7f0464f2084e78b76285593d6~mv2.jpg)
Sunday, December 9, 2018
-
No scheduled construction activity.
Monday, December 10, 2018 - Friday, December 14, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Rhode Island Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from P Street to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from Rhode Island Avenue to P Street NW (west side).
-
Installation of electrical conduit and manholes from W Street to V Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of foundations for TEC cabinets from R Street to Florida Avenue NW (east and west side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, December 15, 2018
-
Relocation of traffic signal cabinet on temporary foundation at the intersection of 14th & P Street NW.
Sunday, December 2 – Saturday, December 8, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, December 8th)
![](https://static.wixstatic.com/media/d5aa8e_94b6b4c83ae540998dc71835704b8614~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_94b6b4c83ae540998dc71835704b8614~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_fd7cbbea603345f0998bf9155d793b4f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_fd7cbbea603345f0998bf9155d793b4f~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_a65af377c976479ba0e39fc7166f9ccc~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_a65af377c976479ba0e39fc7166f9ccc~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_23c024a157a2482eb0072d3fa9fbae6d~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_23c024a157a2482eb0072d3fa9fbae6d~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_61d6424a036a4cfd81670309b2054884~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_61d6424a036a4cfd81670309b2054884~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_1c44e91d67bb48cba44008d62af23595~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_1c44e91d67bb48cba44008d62af23595~mv2.jpg)
Sunday, December 2, 2018
-
No scheduled construction activity.
Monday, December 3, 2018 - Friday, December 7, 2018
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Thomas Circle to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to U Street NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Q Street to U Street NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from Rhode Island Avenue to W Street NW. This activity will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from Rhode Island Avenue to P Street NW (west side).
-
Installation of electrical conduit and manholes from W Street to V Street NW (west side).
-
Installation of fire hydrant at Church Street NW (west side) and Q Street NW (east side).
-
Installation of foundations for TEC cabinets from R Street to Florida Avenue NW (east and west side).
-
Installation of streetlight and traffic signal foundations from Florida Avenue to U Street NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, December 8, 2018
-
Relocation of traffic signal cabinet on temporary foundation at the intersection of 14th & P Street NW.