APRIL 2019
Sunday, April 28 – Saturday, May 4, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, May 4th.
Sunday, April 28, 2019
-
No scheduled construction activity.
Monday, April 29 - Wednesday, May 1, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrants at W Street, V Street and S Street NW.
-
Installation of streetlight and traffic signal foundations at S Street NW and T Street NW.
-
Installation of catch basins at T Street NW (southwest and northwest corners).
-
Reconnecting for water service at R Street to U Street (west side).
-
Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at R Street, S Street, T Street and Florida Avenue NW.
-
Installation of TEC foundation and cabinet at the SE corner of U Street NW.
Thursday, May 2, 2019 - Saturday, May 4, 2019
-
All of the above activities with the exception of the installation of TEC foundation and cabinet at the SE corner of U Street NW.
Sunday, April 21 – Saturday, April 27, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 27th.
![](https://static.wixstatic.com/media/d5aa8e_ad3d02944ec447d1bc0d4693d06819b7~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_ad3d02944ec447d1bc0d4693d06819b7~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_89a782a8918842fa9e95f0bec2ced328~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_89a782a8918842fa9e95f0bec2ced328~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_edcb4f368b164bed9a50f3dd64dff103~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_edcb4f368b164bed9a50f3dd64dff103~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_07c3ef32b64742a1999bc9912e12f8f8~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_07c3ef32b64742a1999bc9912e12f8f8~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_1b2cb5a9729d466bb6322f1da55a8400~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_1b2cb5a9729d466bb6322f1da55a8400~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_0535bf68abaf43dc85fc60d1798fb5e5~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0535bf68abaf43dc85fc60d1798fb5e5~mv2.jpg)
Sunday, April 21, 2019
-
No scheduled construction activity.
Monday, April 22 - Saturday, April 27, 2019
-
Installation of 20-ft poles and 100 watt post top and tear drop fixtures on Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrants at W Street, V Street, S Street, Church Street and Florida Avenue NW.
-
Installation of streetlight and traffic signal foundations at S Street NW and T Street NW.
-
Installation of catch basins at Corcoran Street and T Street NW (southwest and northwest corners).
-
Reconnecting for water service at R Street to U Street (west side).
-
Installation of foundations for traffic control cabinets at Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at R Street, S Street, T Street and Florida Avenue NW.
Sunday, April 14 – Saturday, April 20, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 20th.
![](https://static.wixstatic.com/media/d5aa8e_7e484e68ac294544a2628093dd7a46a3~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_7e484e68ac294544a2628093dd7a46a3~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_b6151d4c3dec4eac8769c73e6dabbdf3~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b6151d4c3dec4eac8769c73e6dabbdf3~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_fea127eb140f490da8b5f26b20259658~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_fea127eb140f490da8b5f26b20259658~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_31d6a52ce561400589c2636383404223~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_31d6a52ce561400589c2636383404223~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_bb56fa8d33414ecca3c69d5369aa7569~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_bb56fa8d33414ecca3c69d5369aa7569~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_dc80b59fcc4f4b4fa52174d57e9a8627~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_dc80b59fcc4f4b4fa52174d57e9a8627~mv2.jpg)
Sunday, April 14, 2019
-
No scheduled construction activity.
Monday, April 15 - Friday, April 19, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks from V Street to Florida Avenue NW (west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.
-
Watermain work at R Street NW (testing and utility markings).
-
Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.
-
Installation of TEC foundation and cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, April 20, 2019
-
All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.
Sunday, April 7 – Saturday, April 13, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 13th.
![](https://static.wixstatic.com/media/d5aa8e_69a4d807a99441b3a45d1994fbe409ff~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_69a4d807a99441b3a45d1994fbe409ff~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_82247bc95218476cb5f51b3f1627891f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_82247bc95218476cb5f51b3f1627891f~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_31189d38c86e470381c00b76a936fed1~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_31189d38c86e470381c00b76a936fed1~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_1cb4ac4172e94acb9a00e8b862308b6a~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_1cb4ac4172e94acb9a00e8b862308b6a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_81a2850e3a1b47fdb0464bc2875e838b~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_81a2850e3a1b47fdb0464bc2875e838b~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_058813ee76d744078a0bdd59d5b15fe7~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_058813ee76d744078a0bdd59d5b15fe7~mv2.jpg)
Sunday, April 7, 2019
-
No scheduled construction activity.
Monday, April 8 - Friday, April 12, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from S Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks at 14th and U Street (east and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.
-
Roadway repair from V Street to Florida Avenue NW. These repairs will be done in a block by block sequence (west side).
-
Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.
-
Installation of TEC cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, April 13, 2019
-
ll of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.
Sunday, March 31 – Saturday, April 6, 2019:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 6th.
![](https://static.wixstatic.com/media/d5aa8e_8a7de28fbca040049b06f8b3704790a1~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_8a7de28fbca040049b06f8b3704790a1~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_464ad799a5904a0e88017c1768d76848~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_464ad799a5904a0e88017c1768d76848~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_c64ac4b9ccb34cf29f8231af6865a78f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_c64ac4b9ccb34cf29f8231af6865a78f~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_1f117123c3004b1fb3643a6789f91f2a~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_1f117123c3004b1fb3643a6789f91f2a~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_4eac2e1456594ee5824722a89471befc~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_4eac2e1456594ee5824722a89471befc~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_b7ee1f46bcba441eab5305eba3b4f279~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b7ee1f46bcba441eab5305eba3b4f279~mv2.jpg)
Sunday, March 31, 2019
-
No scheduled construction activity.
Monday, April 1 - Friday, April 5, 2019
-
Installation of 20-ft poles and 100 watt post top LED fixtures on streetlight foundations from Q Street NW to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Installation of temporary poles from Q Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
-
Removal of streetlight and traffic signal poles from Swann Street to Florida Avenue NW. These removals will be done in a block by block sequence (east side and west side).
-
Transfers from R Street to Florida Avenue. This installation will be done in a block by block sequence (east side and west side).
-
Demolition and installation of sidewalks at 14th and U Street (east and west side).
-
Installation of electrical conduit and manholes at the intersections of T Street and S Street NW (east and west side).
-
Installation of fire hydrant at Q Street, W Street, V Street, U Street, S Street, Church Street and Florida Avenue NW.
-
Roadway repair from V Street to Florida Avenue NW. These repairs will be done in a block by block sequence (west side).
-
Installation of foundations for traffic control cabinets at N Street, Rhode Island Avenue, Q Street, R Street, S Street, T Street, U Street, V Street, W Street and Florida Avenue NW.
-
Installation of traffic control cabinets at N Street, Rhode Island Avenue, R Street, S Street, T Street, W Street and Florida Avenue NW.
-
Installation of TEC cabinet at the SE corner of U Street NW.
-
Installation of streetlight and traffic signal foundations from R Street to Florida Avenue NW. This installation will be done in a block by block sequence (east side and west side).
Saturday, April 6, 2019
-
All of the above activities with the exception of the demolition and installation of sidewalk work will be in progress, pending approval and weather.