APRIL 2018
Sunday, April 22 – Saturday, April 28, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 28th
![](https://static.wixstatic.com/media/d5aa8e_0fb13b2f341b4123ab97b8321a0a972b~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0fb13b2f341b4123ab97b8321a0a972b~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_0df47c77c9574c8eadbbf63b4103e6ad~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0df47c77c9574c8eadbbf63b4103e6ad~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_d78ec313bf694bc480d26639393c3c4f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_d78ec313bf694bc480d26639393c3c4f~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_13d5d1e796744d3d89d3269d618430c9~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_13d5d1e796744d3d89d3269d618430c9~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_c16bb9b7dc3c437fb66e000ea19ddd60~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_c16bb9b7dc3c437fb66e000ea19ddd60~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_ecb9f14bfb9a47e59e3c262016dbd510~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_ecb9f14bfb9a47e59e3c262016dbd510~mv2.jpg)
Sunday, April 22, 2018
-
No scheduled construction activity.
Monday, April 23, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo and install sidewalk from Thomas Circle to N Street NW (east side).
Tuesday, April 24, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo and install sidewalk from Thomas Circle to N Street NW (east side).
Wednesday, April 25, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo and install sidewalk from Thomas Circle to N Street NW (east side).
Thursday, April 26, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo existing curb and gutter from N Street to 1323 (east side).
Friday, April 27, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo existing curb and gutter from N Street to 1323 (east side).
Saturday, April 28, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Q Street NW (northbound lane).
-
Installation of catch basins from N Street to Rhode Island Avenue NW (east side).
-
Demo existing curb and gutter from N Street to 1323 (east side).
Sunday, April 15 – Saturday, April 21, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 21st)
Sunday, April 15, 2018
-
No scheduled construction activity.
Monday, April 16, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
Tuesday, April 17, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
Wednesday, April 18, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).
-
Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).
Thursday, April 19, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).
-
Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).
Friday, April 20, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).
-
Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).
Saturday, April 21, 2018
-
Saw cutting and excavation for electrical conduit from P Street to Church Street NW (northbound lane).
-
Demo existing curb, gutter and sidewalk from N Street to Rhode Island Avenue NW (east side).
Sunday, April 8 – Saturday, April 14, 2018:
Scheduled Activity, Weather Permitting
(PENDING: There is work currently scheduled for Saturday, April 14th)
![](https://static.wixstatic.com/media/d5aa8e_f39bf9e316364d3a9b0ff2fe848279fb~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f39bf9e316364d3a9b0ff2fe848279fb~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_93df72795b9b4bebb759bc47dd7dc8fe~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_93df72795b9b4bebb759bc47dd7dc8fe~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_c93f25e9b26b4ecfbfc397b0f75875fe~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_c93f25e9b26b4ecfbfc397b0f75875fe~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_865b49adc31b474288516a2b6b7bd48b~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_865b49adc31b474288516a2b6b7bd48b~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_c7adc0856627481bbffbbba36174f70e~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_c7adc0856627481bbffbbba36174f70e~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_b8d02597988c4e038e4309722129b607~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_b8d02597988c4e038e4309722129b607~mv2.jpg)
Sunday, April 8, 2018
-
No scheduled construction activity.
Monday, April 9, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Tuesday, April 10, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Layout curb from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Wednesday, April 11, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Thursday, April 12, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Friday, April 13, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Saturday, April 14, 2018
-
Saw cutting and excavation for electrical conduit from Rhode Island Avenue to P Street NW (northbound lane).
-
Installation of street light foundations from Rhode Island Avenue to P Street NW (east side).
-
Demo existing curb, gutter and sidewalk from Thomas Circle to N Street NW (east side).
Sunday, April 1 – Saturday, April 7, 2018:
Scheduled Activity, Weather Permitting
(There is no work currently scheduled for Saturday, April 7th)
![](https://static.wixstatic.com/media/d5aa8e_0fe249935ecf4d9fbb0d9ef25a435303~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0fe249935ecf4d9fbb0d9ef25a435303~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_d69d769cf3ef4b5781bdd092d1224c51~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_d69d769cf3ef4b5781bdd092d1224c51~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_f0a9316a8f064824a30f4d14a56e2302~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_f0a9316a8f064824a30f4d14a56e2302~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_0604bf9641294695827051776c06ca3e~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_0604bf9641294695827051776c06ca3e~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_708b9d1d386a42e6828ae301cc48e248~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_708b9d1d386a42e6828ae301cc48e248~mv2.jpg)
![](https://static.wixstatic.com/media/d5aa8e_7797c016ff3a4ab1909b1803f662de4f~mv2.jpg/v1/fill/w_212,h_212,q_90/d5aa8e_7797c016ff3a4ab1909b1803f662de4f~mv2.jpg)
Sunday, April 1, 2018
-
No scheduled construction activity.
Monday, April 2, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Tuesday, April 3, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Wednesday, April 4, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Thursday, April 5, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Friday, April 6, 2018
-
Saw cutting and excavation for electrical conduit from N Street to Rhode Island Avenue NW (northbound lane).
-
Installation of street light foundation from N Street to Rhode Island Avenue NW (east side).
-
Layout curb from Thomas Circle to Rhode Island Avenue NW (east side).
-
Maintenance of Traffic from Thomas Circle to Rhode Island Avenue (northbound lane).
Saturday, April 7, 2018
-
No scheduled construction activity.